Contractors for the Georgia Department of Transportation (Georgia DOT) will continue construction activities related to the I-16/I-75 Interchange Improvement Project this week in Macon-Bibb County. Weather permitting, the scheduled activities beginning Monday, February 22 through Sunday, February 28, 2021 are listed below.
New Lane Closures/ Traffic Shifts:
- None scheduled
Ongoing, Long-term Closures:
- The dedicated right turn lane on the I-16 eastbound off-ramp to Spring Street will remain closed through the spring of 2021.
- The permanent lane closure on Coliseum Drive/Martin Luther King, Jr. Boulevard southbound between Clinton Street to Riverside Drive; southbound traffic in that area is currently reduced to one lane.
- The far right lane of I-75 northbound at the Georgia 19/Georgia Avenue exit (exit 164) is closed to traffic for several months.
- Spring Street’s far right lane at the I-16 westbound on-ramp as well as the right-hand on-ramp to I-16 westbound are both closed for several months; the Spring Street on-ramp to I-16 westbound has been relocated to the far left lane.
Construction Activities for February 22-28, weather and on-site conditions permitting:
Phase 2 and 3: I-75 from Hardeman Avenue to I-16 eastbound
- Crews continue construction of the Riverside Bridge superstructure over I-75 and the Walnut Street bridge stage two superstructure;
- Continue construction of the new I-75 northbound bridge;
- Continue construction of new I-75 southbound bridge superstructure;
- Continue working on superstructure of the I-16 westbound bridge over the Ocmulgee River;
- Continue construction of two new I-16 westbound to I-75 southbound bridge superstructures;
- Construction of MSE (retaining) walls along I-75 northbound and southbound and at other locations throughout the project continues;
- Construction of concrete sound and visual walls along I-75 northbound and southbound continues;
- Continue demolition of the concrete pavement on the left lane on I-75 southbound from the Riverside Drive bridge to the Hardeman Avenue bridge;
- Continue demolition of the existing pavement on the left lanes of I-75 northbound from Hardeman Avenue to north of the Riverside Bridge;
- Continue grading subgrade and placing gravel mixture in the median of I-75 northbound and southbound from Hardeman Avenue to Riverside Drive and from the new I-16 westbound ramp to the new I-75 southbound ramp;
- Continue installation of light poles on the new I-16 westbound ramp;
- Continue asphalt paving on the new I-16 westbound lanes and ramps to I-75 northbound and southbound; and
- Continue concrete paving on the new I-16 westbound to I-75 northbound and southbound lanes.
Phase 1: I-16 from the I-16/ I-75 split to the Martin Luther King Jr. Boulevard exit
- Crews continue work on the superstructure for the bridge along I-16 eastbound near Spring Street;
- Construction continues on the superstructure for the new I-16 eastbound bridge over the Ocmulgee River;
- Construction continues on the second stage of the new Martin Luther King Jr. Boulevard bridge over the Ocmulgee River;
- Construction continues on the new I-16 eastbound bridge superstructure over Norfolk Southern Railroad;
- Construction continues on the superstructure for the new I-16 eastbound bridge over Spring Street;
- Construction continues on MSE (retaining) walls along I-16 eastbound between Spring Street and Martin Luther King Jr. Boulevard;
- Grading activities continue on the I-16 eastbound exit ramps to Martin Luther King, Jr. Boulevard and Spring Street; and
- Grading activities continue on the entrance ramp to I-16 eastbound from Martin Luther King Jr. Boulevard.
The I-16/I-75 Interchange Improvements Project is a $500 million safety and mobility megaproject. With its massive scope to widen and reconstruct I-16, I-75 and their interchange in Macon-Bibb County, this project is being delivered in seven design and construction phases that will continue through 2030. When complete, new CD lanes, additional interstate lanes, new interstate on-and off-ramps, upgrades to 11 bridges, new walls, upgraded drainage systems, etc. will deliver safer and improved mobility for Macon-Bibb County’s local commuters and businesses, regional travelers and commercial freight from the Georgia southern coast to destinations within the state and throughout the U.S.
Advisory: Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones.
For more I-75 travel info, visit www.i75exitguide.com, the Internet’s largest and most complete website devoted to I-75, America’s Interstate Main Street. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit from Michigan to Florida! Plus I-75 construction, real-time traffic and road news.