Georgia’s I-16/I-75 Interchange Project Updates for February 22-28, 2021:

2075
I-75 Georgia Road Construction | I-75 Exit Guide

Contractors for the Georgia Department of Transportation (Georgia DOT) will continue construction activities related to the I-16/I-75 Interchange Improvement Project this week in Macon-Bibb County. Weather permitting, the scheduled activities beginning Monday, February 22 through Sunday, February 28, 2021 are listed below.

New Lane Closures/ Traffic Shifts:

  • None scheduled

Ongoing, Long-term Closures:

  • The dedicated right turn lane on the I-16 eastbound off-ramp to Spring Street will remain closed through the spring of 2021.
  • The permanent lane closure on Coliseum Drive/Martin Luther King, Jr. Boulevard southbound between Clinton Street to Riverside Drive; southbound traffic in that area is currently reduced to one lane.
  • The far right lane of I-75 northbound at the Georgia 19/Georgia Avenue exit (exit 164) is closed to traffic for several months.
  • Spring Street’s far right lane at the I-16 westbound on-ramp as well as the right-hand on-ramp to I-16 westbound are both closed for several months; the Spring Street on-ramp to I-16 westbound has been relocated to the far left lane.

Construction Activities for February 22-28, weather and on-site conditions permitting:

Phase 2 and 3: I-75 from Hardeman Avenue to I-16 eastbound

  • Crews continue construction of the Riverside Bridge superstructure over I-75 and the Walnut Street bridge stage two superstructure;
  • Continue construction of the new I-75 northbound bridge;
  • Continue construction of new I-75 southbound bridge superstructure;
  • Continue working on superstructure of the I-16 westbound bridge over the Ocmulgee River;
  • Continue construction of two new I-16 westbound to I-75 southbound bridge superstructures;
  • Construction of MSE (retaining) walls along I-75 northbound and southbound and at other locations throughout the project continues;
  • Construction of concrete sound and visual walls along I-75 northbound and southbound continues;
  • Continue demolition of the concrete pavement on the left lane on I-75 southbound from the Riverside Drive bridge to the Hardeman Avenue bridge;
  • Continue demolition of the existing pavement on the left lanes of I-75 northbound from Hardeman Avenue to north of the Riverside Bridge;
  • Continue grading subgrade and placing gravel mixture in the median of I-75 northbound and southbound from Hardeman Avenue to Riverside Drive and from the new I-16 westbound ramp to the new I-75 southbound ramp;
  • Continue installation of light poles on the new I-16 westbound ramp;
  • Continue asphalt paving on the new I-16 westbound lanes and ramps to I-75 northbound and southbound; and
  • Continue concrete paving on the new I-16 westbound to I-75 northbound and southbound lanes.

Phase 1: I-16 from the I-16/ I-75 split to the Martin Luther King Jr. Boulevard exit

  • Crews continue work on the superstructure for the bridge along I-16 eastbound near Spring Street;
  • Construction continues on the superstructure for the new I-16 eastbound bridge over the Ocmulgee River;
  • Construction continues on the second stage of the new Martin Luther King Jr. Boulevard bridge over the Ocmulgee River;
  • Construction continues on the new I-16 eastbound bridge superstructure over Norfolk Southern Railroad;
  • Construction continues on the superstructure for the new I-16 eastbound bridge over Spring Street;
  • Construction continues on MSE (retaining) walls along I-16 eastbound between Spring Street and Martin Luther King Jr. Boulevard;
  • Grading activities continue on the I-16 eastbound exit ramps to Martin Luther King, Jr. Boulevard and Spring Street; and
  • Grading activities continue on the entrance ramp to I-16 eastbound from Martin Luther King Jr. Boulevard.

The I-16/I-75 Interchange Improvements Project is a $500 million safety and mobility megaproject. With its massive scope to widen and reconstruct I-16, I-75 and their interchange in Macon-Bibb County, this project is being delivered in seven design and construction phases that will continue through 2030. When complete, new CD lanes, additional interstate lanes, new interstate on-and off-ramps, upgrades to 11 bridges, new walls, upgraded drainage systems, etc. will deliver safer and improved mobility for Macon-Bibb County’s local commuters and businesses, regional travelers and commercial freight from the Georgia southern coast to destinations within the state and throughout the U.S.

Advisory: Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones.


For more I-75 travel info, visit  www.i75exitguide.com, the Internet’s largest and most complete website devoted to I-75, America’s Interstate Main Street. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit from Michigan to Florida! Plus I-75 construction, real-time traffic and road news.

Previous articleLane Closures for I-75 Construction in Tennessee This Week
Next articleLarger Than Life Whale Exhibit Coming to Clearwater Marine Aquarium
I-75 Exit Guide
One of the most complete road travel resources of its kind on the Internet! The Interstate 75 Exit Information Guide features exit service listings for the entire length of I-75 from Michigan to Florida! Food, gas, lodging, rest areas, attractions and more…