The Florida Department of Transportation (FDOT) reports the following I-75 construction activities at Big Bend Road (CR672) in the Tampa Bay area. All work is weather dependent and subject to change.
I-75 ramps construction activities:
- I-75 southbound exit ramp to eastbound Big Bend Road (Ramp A):
- Placement of asphalt pavement north of Big Bend Rd; completed
- I-75 southbound exit ramp to westbound Big Bend Road (Ramp A-1):
- Embankment operations; ongoing
- Drainage installation; completed
- I-75 southbound entrance ramp from westbound Big Bend Road (Ramp B):
- Construction activities; begins fall of 2023
- I-75 southbound entrance ramp from eastbound Big Bend Road (Ramp B-1):
- Construction activities; begins fall of 2023
- I-75 northbound exit ramp to westbound Big Bend Road (Ramp C):
- Construction activities; begins late summer of 2023
- I-75 northbound exit ramp to eastbound Big Bend Road (Ramp C-1):
- Construction activities; begins late summer of 2023
- I-75 northbound entrance ramp from eastbound Big Bend Road (Ramp D):
- Mechanically Stabilized Earth (MSE) wall installation; ongoing
- Stabilization operations; ongoing
- I-75 northbound entrance ramp from westbound Big Bend Road (Ramp D-1):
- Placement of earthwork material; ongoing
- Pile driving; Phase 1 completed; Phase 2 begins summer 2023
- Abutment and end wall construction; ongoing
Bridge and pedestrian tunnel construction activities:
- Old Big Bend Road bridge over Bullfrog Creek (Bridge 1):
- Pile driving; completed
- Bridge substructure; nearing completion
- Girder installation; begins spring 2023
- I-75 northbound entrance ramp (Ramp D1 & Big Bend Road) over Bullfrog Creek (Bridge 2):
- Phase 1 pile driving; completed
- Phase 1 substructure; nearing completion
- Phase 1 girder erection; begins spring 2023
- Phase 2 pile driving; begins summer 2023
- I-75 southbound exit ramp (Ramp A) over Old Big Bend Road/Big Bend Road (Bridge 3):
- Pier construction; completed
- I-75 southbound exit ramp (Ramp A-1) over Old Big Bend Road (Bridge 4):
- Abutment construction; ongoing
- I-75 northbound entrance ramp (Ramp D & D1) over Old Big Bend Road (Bridge 5):
- Substructure construction; completed
- Girder erection; begins spring 2023
- Pedestrian tunnel under the I-75 northbound entrance ramp (Bridge 6):
- Construction activities; begins spring 2023
Roadway construction activities:
- Big Bend Road:
- Installation of 36” water main; ongoing
- Utility jack and bores; ongoing
- Stormwater installation; ongoing
- Old Big Bend Road:
- New bridge construction over Bullfrog Creek; ongoing
- Wet utility relocation activities; nearing completion
- Stormwater installation; ongoing
- Future roadway reconstruction; ongoing
- Slope pavement under I-75; nearing completion
- Stabilization operations; ongoing
- Bullfrog Creek Road:
- YMCA Pond 1; ongoing
- Future roadway reconstruction; ongoing
- Drainage installation; ongoing
Ongoing construction activities throughout the project limits:
- Asphalt pavement operations
- Bridge substructure installation
- Embankment operations
- Highway lighting installation
- Jack and bore operations
- Mechanically Stabilized Earth (MSE) wall installation
- Storm drainage and wet utility installation
- Maintenance of traffic control devices, erosion control, and litter removal
The I-75 Exit Guide is the Internet’s largest and most complete website dedicated to Interstate 75 travelers. Find detailed exit service listings… lodging, camping, food, gas and more for every exit from Michigan to Florida!
On the road? Why not take us with you. The I-75 Exit Guide is mobile-friendly and totally FREE. No App Required.
Traveling another route? Visit our growing family of exit guides: I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-75 Exit Guide, I-80 Exit Guide and I-95 Exit Guide. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit along the way!