Contractors for the Georgia Department of Transportation (GDOT) will continue construction activities related to the I-16/I-75 Interchange Improvement Project in Macon-Bibb. Weather permitting, the scheduled activities beginning Monday, April 18 through Sunday, April 24, 2022 are listed below.
Lane Closures, Traffic Shifts:
Monday through Friday, April 18-22
- Single left lane closures on I-75 northbound and southbound between US 41/Forsyth Street/Hardeman Avenue and SR 247/Pierce Avenue beginning at 9 p.m. until 5 a.m. the following mornings. Emergency vehicles will periodically pace traffic to achieve slower, safer speeds through the area as workers install overhead roadway signs and pave asphalt.
- Single left lane closures on I-16 eastbound and westbound between the I-16/I-75 interchange and the Spring Street exit from 9 a.m. until 5 a.m. the following mornings. Traffic will be paced for slower, safer speeds as crews work in the road median.
Sunday, April 24 (tentative)
- Overnight shift of traffic on Otis Redding Bridge, new lanes open to traffic in preparation for the Bridge’s new six-lane configuration (three lanes in each direction):
- Westbound lanes will be shifted onto newly constructed lanes, and the dedicated left turn lane onto Riverside Drive will be open to traffic
- Three eastbound lanes will be open to traffic on newly constructed roadway
Ongoing, Long-term Closures:
- The permanent lane closure on Coliseum Drive/Martin Luther King, Jr. Boulevard southbound between Clinton Street to Riverside Drive; southbound traffic in that area is currently reduced to one lane.
- The far-right lane of I-75 northbound at the Georgia 19/Georgia Avenue exit (exit 164) is closed to traffic for several months.
- Spring Street’s far right lane at the I-16 westbound on-ramp as well as the right-hand on-ramp to I-16 westbound are both closed for several months; the Spring Street on-ramp to I-16 westbound has been relocated to the far left lane.
Construction Activities for April 18-24, weather and on-site conditions permitting:
Phases 4 and 5: from I-16 westbound/I-75 to Walnut Creek
- Continue construction of new Second Street bridge substructure.
- Continue construction of three new I-16 westbound bridge substructures.
- Continue construction of three new I-16 eastbound bridge substructures.
- Continue construction of two new I-16 westbound entrance ramps.
- Continue construction of new MSE (retaining) walls along I-75 northbound and southbound and other walls throughout the project.
Phase 2 and 3: I-75 from Hardeman Avenue to I-16 eastbound
- Completed construction of the Riverside Bridge superstructure over I-75.
- Continue construction of the Walnut Street bridge over I-75 stage two superstructure.
- Continue construction of the superstructure for new I-75 northbound and southbound bridges.
- Continue construction of the substructure for new I-75 northbound and southbound bridges.
- Continue demolition and removal of the existing I-16 westbound and I-75 northbound and southbound bridges.
- Construction of MSE (retaining) walls along I-75 northbound and southbound and at other locations throughout the project continues.
- Construction of concrete sound and visual walls along I-75 northbound and southbound continues.
- Continue demolition of the existing pavement on the left lanes of I-75 northbound from Hardeman Avenue to north of the Riverside Bridge.
- Continue concrete paving for the new I-75 southbound exit ramp to the new I-16 entrance ramp.
- Continue concrete paving for the new I-75 northbound and southbound roadways.
Phase 1: I-16 from the I-16/ I-75 split to the Martin Luther King Jr. Boulevard exit
- Continue constructing the new Martin Luther King Jr. Boulevard Bridge over the Ocmulgee River second stage superstructure.
- Continue grading near Martin Luther King Jr. Boulevard /Coliseum Drive.
- Continue installing lights on Martin Luther King Jr. Boulevard and Spring Street.
The I-16/I-75 Interchange Improvement Project is a $500 million safety and mobility megaproject. With its massive scope to widen and reconstruct I-16, I-75 and their interchange in Macon-Bibb, this project is being delivered in seven design and construction phases that will continue through 2030. When complete, new CD lanes, additional interstate lanes, new interstate on-and off-ramps, upgrades to 11 bridges, new walls, upgraded drainage systems, etc. will deliver safer and improved mobility for Macon-Bibb’s local commuters and businesses, regional travelers and commercial freight from the Georgia southern coast to destinations within the state and throughout the U.S.
Advisory: Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
For more I-75 information, visit www.i75exitguide.com, the Internet’s largest and most complete website devoted to America’s Interstate 75. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit from Michigan to Florida!
Traveling another route? Visit our growing family of exit guides: I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-80 Exit Guide and I-95 Exit Guide.