This report is prepared by the Florida Department of Transportation (FDOT) to inform the public about upcoming road work on I-75 in Southwest Florida. Below are the work schedule and lane closure locations for I-75 projects.

I-75 from mile marker 76 to the mile marker 100/Toll Plaza
Construction project: Crews will widen and resurface the roadway as well as construct new guardrail and wildlife crossings.

Motorists should expect intermittent southbound and northbound lane closures during daytime hours throughout the duration of the project.

Motorists should use caution as crews work on the roadway. The expected project completion is spring 2024.

I-75 from the Broward County line to the east of the bridge over Wildlife Crossing #15
Construction project: Crews will widen and resurface the roadway as well as construct new guardrail and wildlife crossings.
Motorists should expect daytime ramp closures at the Recreational Area at MM 70 on I-75 northbound from 7 a.m. to 6 p.m. for guardrail repairs.

Motorists should expect intermittent southbound and northbound lane closures during daytime hours throughout the duration of the project.

Motorists should use caution as crews work on the roadway. The expected project completion is spring 2024.

I-75 at SR 951 (exit 101) Interchange Improvements
FDOT is reconstructing the I75 southbound on and off-ramp connections and the northbound on-ramp connection to the mainline lanes at SR 951 (exit 101). The northeast quadrant loop ramp will be connected to, and accessible only by, a direct flyover ramp from northbound Collier Boulevard starting south of the Davis Boulevard intersection. This single-lane flyover ramp will carry traffic over Beck Boulevard and a reconstructed I-75 southbound on-ramp. A single-lane flyover ramp extension will carry I-75 southbound traffic over Davis Boulevard to a new signalized intersection at Collier Boulevard and Business Circle North. This ramp will extend along the western side of Collier Boulevard.

Crews are also currently constructing the noise wall on the south side of I-75, just west of the interchange. The contractor does not expect impacts to traffic with this activity.

Crews are also currently working at northbound SR 951 at the I-75 southbound on-ramp. Motorists should expect truck traffic during daytime hours. The contractor does not expect impacts to traffic with this activity.

Please use caution and watch for workers and construction vehicles entering and leaving the roadway. The expected completion date is spring 2026.


What’s happening on Interstate 75 RIGHT NOW! I-75 Real-time traffic information for selected cities along I-75. Maps show updates on road construction, traffic accidents, travel delays and the latest traffic speeds. Traffic cameras show congestion at a glance. Visit I-75 Traffic.


The I-75 Exit Guide is the Internet’s largest and most complete website dedicated to Interstate 75 travelers. Find detailed exit service listings… lodging, camping, food, gas and more for every exit from Michigan to Florida!

On the road? Why not take us with you. The I-75 Exit Guide is mobile-friendly and totally FREE. No App Required.

Traveling another route? Visit our growing family of exit guides:  I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-75 Exit Guide, I-80 Exit Guide and I-95 Exit Guide. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit along the way!

Previous articleLookout Mountain Incline Railway – Chattanooga, TN
Next articleNew I-75 Ramp to Big Bend Road Opening Tuesday Morning
I-75 Exit Guide
One of the most complete road travel resources of its kind on the Internet! The Interstate 75 Exit Information Guide features exit service listings for the entire length of I-75 from Michigan to Florida! Food, gas, lodging, rest areas, attractions and more…